One of two steam turbine generators will be overhauled at the Jamestown Board of Public Utilities. On Monday, the BPU approved contracting with S.T. Cotter Turbine Services of Clearwater, Minn., to perform a maintenance overhaul of steam turbine generator No. 5 in the amount of $1.9 million. According to the resolution approved by the BPU, S.T. Cotter Turbine Services was the lowest of seven bids, which ranged between $1.9 million and $4 million.

S.T. Cotter was the lowest bid, which included part
Source: NDT